Contact Us

In This Department

Topics of Interest

Department Home

More Information

Projects Under Construction

Click here to be directed to an interactive map of current projects (Beta Version).

Road/Drainage Projects

Project Number Project Name Contract Amount Contractor Complete Expected Completion Date
22-11-01 96" Storm Sewer Repairs - Southeast side $3,427,919.00 Culy Contracting LLC 90%
23-004 2023 Dresden Street Outfall Repairs $816,800.00 Blankenberger Bros 95%
23-024 Evansville East Side Drainage Project Phase 1 $2,713,063.00 Blankenberger Brothers Inc 5%
24-019 Stinson Ave Drainage Improvements $172,065 Koberstein Contracting Inc 90%
24-021 Mt Vernon Rd and Riggs Ave Pipe Joint Repair $33,800 Blanuenberger Brothers Inc 0%

Paving Projects

Project No. Project Name Contract Amount Contractor Complete Expected Completion Date
23-022 Lynch Road and Career Avenue Traffic Signal Installation $225,150.00 Ragel Construction 90% Dec 2024
23-025 Bob Jones Way Brick Paver Failure Remediation $204,874.95 River Town Construction LLC 60% Nov 2024
24-002 2024 Mill and Overlay - Phase 2 $1,540,381.43 RH Rudolph and Co Inc 20% Dec 2024
24-011 2024 Paving Phase 3 $1,381,655.77 E&B Paving LLC 0% May 2025
24-018 2024 Neighborhood Patching $82,686.25 Jerry David Enterprises 80%

2024 Paving TBD - (Subject to Funding Availability) 

Street Name Parameters
Fulton Buena Vista to Mill
Fulton Cody to Pigeon
Campground Rd                Cemetery to Old State
Hitch Peters                       Lynch to St George
Allens Lane Railroad tracks to Kratzville
N Barker                             Franklin to Mt Vernon

2025 Paving TBD - (Subject to Funding Availability) 

Street Name Parameters
Court Street                       Riverside to Martin Luther King Jr.
E. Mill Road                        Weaver to Kentucky
Lincoln                                 Rotherwood to Weinbach
Lynch                                    Maxx to Debbie
N. 1st                                      Division to Columbia
N. Garvin                             Division to Missouri
N. Kentucky                       Joan to Cardinal
Martin Luther King Jr      Court to Liberty Way
St George                            New York to Harlan
Washington                        Putnam to St James
Washington                        Green River to Newburgh
Main                                       4th to 5th 

Sidewalks and Curb Ramps

Project No Project Name Contract Amount Contractor Complete Expected Completion Date
23-027 2023 ADA Curb Ramps $287,888.40 River Town Construction LLC 95% August 2024
24-009 2024 ADA Curb Ramp Improvements River Town Construction LLC 0%
24-017 2024 Barrett Law

$82,864.60

River Town Construction LLC 80%

Federal Aid Project - 80% Federally Funded

Project Name Construction Inspector Contractor Complete Expected Completion Date
Walnut 3 Structurepoint Blankenberger Brothers 35% September 2025

** Please see the below the estimated Walnut Street Construction timeline:

  • PHASE 1:  US 41 to Weinbach Avenue
    Construction is complete.  
  • PHASE 2:  Weinbach to Vann Avenue
    Construction is ongoing. Expected Completion by the end of 2023 
  • Phase 3:  US 41 to Martin Luther King Jr. Boulevard
    Project has been bid and awarded to Blankenberger 
  • Phase I at US 41 will start by the end of July 2023. 
    Utility relocations have begun.