Click here to be directed to an interactive map of current projects (Beta Version).
Road/Drainage Projects
|
Project Number |
Project Name |
Contract Amount |
Contractor |
Complete |
Expected Completion Date |
23-004 |
2023 Dresden Street Outfall Repairs |
$816,800.00 |
Blankenberger Bros |
95% |
|
22-11-01 |
96" Storm Sewer Repairs - Southeast side |
$3,427,919.00 |
Culy Contracting LLC |
66% |
|
23-024 |
Evansville East Side Drainage Project Phase 1 |
$2,713,063.00 |
Blankenberger Brothers Inc |
5% |
|
23-003 |
Division Street Extension |
$975,316.29 |
Dieg Brothers Lumber and Construction Co Inc |
95% |
September 2024 |
Paving Projects
|
Project No. |
Project Name |
Contract Amount |
Contractor |
Complete |
Expected Completion Date |
23-022 |
Lynch Road and Career Avenue Traffic Signal Installation |
$225,150.00 |
Ragel Construction |
0% |
Dec 2024 |
23-025 |
Bob Jones Way Brick Paver Failure Remediation |
$204,874.95 |
River Town Construction LLC |
60% |
Nov 2024 |
24-002 |
2024 Mill and Overlay - Phase 2 |
$1,540,381.43 |
RH Rudolph and Co Inc |
20% |
Dec 2024 |
24-011 |
2024 Paving Phase 3 |
$1,381,655.77 |
E&B Paving LLC |
0% |
May 2025 |
2024 Paving TBD - (Subject to Funding Availability)
|
Street Name |
Parameters |
Fulton |
Buena Vista to Mill |
Fulton |
Cody to Pigeon |
Campground Rd |
Cemetery to Old State |
Hitch Peters |
Lynch to St George |
Allens Lane |
Railroad tracks to Kratzville |
N Barker |
Franklin to Mt Vernon |
2025 Paving TBD - (Subject to Funding Availability)
|
Street Name |
Parameters |
Court Street |
Riverside to Martin Luther King Jr. |
E. Mill Road |
Weaver to Kentucky |
Lincoln |
Rotherwood to Weinbach |
Lynch |
Maxx to Debbie |
N. 1st |
Division to Columbia |
N. Garvin |
Division to Missouri |
N. Kentucky |
Joan to Cardinal |
Martin Luther King Jr |
Court to Liberty Way |
St George |
New York to Harlan |
Washington |
Putnam to St James |
Washington |
Green River to Newburgh |
Main |
4th to 5th |
Sidewalks and Curb Ramps
|
Project No |
Project Name |
Contract Amount |
Contractor |
Complete |
Expected Completion Date |
23-027 |
2023 ADA Curb Ramps |
$287,888.40 |
River Town Construction LLC |
95% |
August 2024 |
24-009 |
2024 ADA Curb Ramp Improvements |
|
River Town Construction LLC |
0% |
|
24-017 |
2024 Barrett Law |
|
|
|
|
Federal Aid Project - 80% Federally Funded
|
Project Name |
Construction Inspector |
Contractor |
Complete |
Expected Completion Date |
Walnut 3 |
Structurepoint |
Blankenberger Brothers |
35% |
September 2025 |
** Please see the below the estimated Walnut Street Construction timeline:
- PHASE 1: US 41 to Weinbach Avenue
Construction is complete.
- PHASE 2: Weinbach to Vann Avenue
Construction is ongoing. Expected Completion by the end of 2023
- Phase 3: US 41 to Martin Luther King Jr. Boulevard
Project has been bid and awarded to Blankenberger
- Phase I at US 41 will start by the end of July 2023.
Utility relocations have begun.